You finalize a meter replacement after you have replaced the physical meter that is monitored by the meter object. When you finalize a meter replacement, the meter object starts logging and collecting values from the physical meter.
Update the configuration of the monitored variable if the new physical meter is exposed using a different address or register.
Do one of the following:
In WorkStation, right-click the meter object, point to Meter management then click Finalize meter replacement .
In WebStation, right-click the meter object, then click Finalize meter replacement .
Specify the start value and the maximum value for the new meter in the dialog box.
Click OK .